Project information
- Country: United Kingdom
- Category: Offshore Wind
- Client: Ørsted & Siemens Gamesa RE
- Final Client: Ørsted
- Project date: 2015-2018
- Project: 4C Offshore
Since its commissioning in 2018, this was the largest offshore wind farm project in the world until 2022 with a total capacity of approximately 1.218 MW. The project consists of 174x 7.0 Siemens Gamesa wind turbines, one offshore substation, one reactive compensation station and one onshore substation.
From early design phase until hand-over to operations, we have managed the entire high voltage equipment scope in the offshore substation. Aditionally, we have provided support during design and testing phase for WTG OEM in the areas of WTG SCADA and grid compliance.